Mathematics · Levelling and Surveying Calculations
A levelling process is carried out to establish the Reduced Level (RL) of point R with respect to the Bench Mark (BM) at P. The staff readings taken are: Station P: BS = 1.655 m, RL = 100.000 m Station Q: BS = -0.950 m, FS = -1.500 m Station R: FS = 0.750 m If the RL of P is +100.000 m, then the RL (in m) of R is:
- 1103.355
- 2103.155
- 3101.455✓
- 4100.355
Correct answer
101.455
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length Mathematics mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Levelling and Surveying Calculations?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Levelling and Surveying Calculations