Computer Science · Project Management
A key stakeholder requests to add a new feature after project planning is finalized. This addition would delay the current timeline, but it aligns with the core business goals. What should the project manager do first?
- 1Ask the team to work extra hours to include it without adjustments
- 2Reject the request completely since planning is completed
- 3Initiate formal change control procedures to assess the impact on scope, cost, and timeline✓
- 4Immediately add the feature to show flexibility to the stakeholder
Correct answer
Initiate formal change control procedures to assess the impact on scope, cost, and timeline
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer Science?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer Science · Project Management