Law · Limitation Act, 1963
A judgment was passed on 10/07/2002, and the decree was prepared on 25/07/2002. An application for a certified copy was made on 11/07/2002, the certified copy was ready on 01/08/2002, and delivery of the certified copy was taken on 05/08/2002. Under Section 12, the period to be excluded as time requisite for obtaining a copy of the decree is:
- 111/07/2002 to 01/08/2002✓
- 211/07/2002 to 05/08/2002
- 310/07/2002 to 01/08/2002
- 410/07/2002 to 05/08/2002
Correct answer
11/07/2002 to 01/08/2002
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Law?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Limitation Act, 1963?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Law · Limitation Act, 1963