Mathematics · Time and Work
A is 4 times as efficient as B. If A completes a work in 45 days less than B, in how many days can they finish the work together?
- 112 days✓
- 216 days
- 315 days
- 414 days
Correct answer
12 days
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Time and Work?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Time and Work