Accounting · Capital and Revenue Expenditure
A heavy engineering firm is acquiring a plot of land for a new foundry. The negotiated purchase price is Rs 10,00,00,000. The firm incurs the following additional costs: Rs 80,00,000 for stamp duty and registration, Rs 5,00,000 for a legal title search, Rs 15,00,000 for leveling the land and removing old hazardous waste, and Rs 12,00,000 for constructing a boundary wall. To fund the purchase, the firm takes a loan and pays Rs 8,00,000 in loan processing fees. Additionally, the seller had unpaid property taxes of Rs 4,00,000 for the previous three years, which the buyer agreed to pay as part of the deal. Finally, a Rs 2,00,000 fee was paid to a real estate broker. Calculate the final value of the land in the books of accounts.
- 1Rs 11,26,00,000
- 2Rs 11,14,00,000
- 3Rs 11,18,00,000✓
- 4Rs 11,10,00,000
Correct answer
Rs 11,18,00,000
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Accounting?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Capital and Revenue Expenditure?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Accounting · Capital and Revenue Expenditure