Mathematics · Time and Work
A group of 12 workers can complete a construction project in 15 days. If the project deadline is shortened, and the same group of workers now needs to complete the project in 9 days, how many additional workers should be added to the group to meet the new deadline?
- 18✓
- 212
- 310
- 49
Correct answer
8