A generating station supplies power through four feeders. The maximum demands for the four feeders are 16 MW, 10 MW, 12 MW, and 7 MW respectively. If the overall maximum demand on the generating station is 15 MW and the load factor is 60%, find (a) the value of diversity factor and (b) the number of units generated annually.
- 1a) 3.00 and b) 78,840 MWh✓
- 2a) 3.00 and b) 12,000 MWh
- 3a) 2.25 and b) 78,840 MWh
- 4a) 2.25 and b) 12,000 MWh
Correct answer
a) 3.00 and b) 78,840 MWh
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Power Generation Economics?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Power Generation Economics