A Gantt chart:
- 1consists of two axes, where x-axis generally represents activities and y-axis represents facilities
- 2is a very useful graphical tool and one of the first scientific techniques for project planning and scheduling✓
- 3is related to the operating characteristic curve to understand how effective a particular sampling plan is
- 4is unsuitable for any non-production activity involving multiple project activities
Correct answer
is a very useful graphical tool and one of the first scientific techniques for project planning and scheduling
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Industrial Engineering?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Industrial Engineering · Project Management