A fundamental assumption underpinning the Critical Path Method (CPM) that differentiates it from PERT is:
- 1Its primary objective being to identify potential deterrents and modify the plan refinement.
- 2The emphasis on quantifying the effects of human factors and psychological variables.
- 3The belief that the duration of each activity is fixed and known with certainty.✓
- 4The recognition of uncertainty in task durations, making time a variable in the analysis.
Correct answer
The belief that the duration of each activity is fixed and known with certainty.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Management?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Management · Project Management