A factory has three work centres arranged in a series for a particular product. The raw material passes through the work centres successively. If the times required at the three work centres are 1.6 s, 1.4 s, and 1.2 s respectively, the system efficiency is:
- 185%
- 287.5%✓
- 392%
- 480%
Correct answer
87.5%