A does 7/10 part of a work in 15 days. After that, he completes the remaining work in 4 days with the help of B. In how many days will A and B together do the same work?
- 18 1/4 days
- 213 1/3 days✓
- 312 2/3 days
- 410 1/3 days
Correct answer
13 1/3 days