General Studies · Project Management
A 'Critical Path' in Critical Path Method (CPM) project management is defined as:
- 1The path with the most non-essential activities
- 2The sequence of activities where a delay does not affect the project timeline
- 3The long sequence of interdependent activities that dictates the overall project duration✓
- 4The path that utilizes the least amount of human resources
Correct answer
The long sequence of interdependent activities that dictates the overall project duration
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management