Computer · Construction Management
A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount of Rs. 54,000. Consider the following statements: P: It is economically advisable to complete the activity early by crashing if the indirect cost of the project is Rs. 8,500 per day. Q: It is economically advisable to complete the activity early by crashing if the indirect cost of the project is Rs. 10,000 per day. Which one of the following options is CORRECT?
- 1P is true and Q is false
- 2Both P and Q are false
- 3P is false and Q is true
- 4Both P and Q are true✓
Correct answer
Both P and Q are true
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management