A cost centre has an overhead absorption rate of $4.25 per machine hour, based on a budgeted activity level of 12,400 machine hours. In the period covered by the budget, actual machine hours worked were 2% more than the budgeted hours and the actual overhead expenditure incurred in the cost centre was $56,389. What was the total over or under absorption of overheads in the cost centre for the period?
- 1$3,689 under absorbed
- 2$3,689 over absorbed
- 3$2,635 under absorbed✓
- 4$1,054 over absorbed
Correct answer
$2,635 under absorbed
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Accounting?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Management Accounting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Accounting · Management Accounting