A contractor undertakes to complete a building work in 250 days. He employs 300 persons for 50 days and they complete half of the work. He then reduces the number of persons to 100, who work for 120 days, after which there are 20 days of holidays. How many persons must be employed for the remaining period to finish the work on time?
- 150✓
- 270
- 348
- 465
Correct answer
50