Mathematics · Time and Work
A contractor undertakes to build a wall in 50 days. He employs 50 men for the same. However, after 25 days he finds that the work is only 40% complete. How many more men need to be employed to complete the work 10 days before the scheduled time?
- 1125
- 2115
- 395
- 475✓
Correct answer
75
Download Single Question PDF