A contractor undertakes to build a school building in 40 days. He employs 100 men in the beginning and 100 more men after 35 days, completing the construction within the stipulated time. If he had not employed the additional men, how many days behind schedule would the school building have been completed?
- 15 days✓
- 24 days
- 33 days
- 42 days
Correct answer
5 days