A contractor undertakes to build a mall in 60 days and employs 30 men. After 30 days, it is found that only one-third of the work is completed. How many extra men should he employ so that the work is completed on time?
- 140 men
- 230 men✓
- 325 men
- 420 men
Correct answer
30 men