A contractor employs 15 men to complete a work in 24 days, working 8 hours per day. After 6 days, he adds 5 more men and reduces the working hours to 6 hours per day from the 7th day onwards. If all men work with the same efficiency, how many more days will be required to finish the remaining work?
- 122
- 221
- 318✓
- 420
Correct answer
18