A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km of the road had been completed. How many additional people would he need to employ in order to finish the work exactly on time?
- 180
- 260
- 350
- 440✓
Correct answer
40