A contractor agreed to construct a 6 km road in 200 days and employed 140 workers for the task. After 60 days, he found that only 1.5 km of the road had been completed. How many additional workers must he employ to finish the remaining work on time?
- 130
- 240✓
- 350
- 460
Correct answer
40