A contract related to cleaning debris around a construction site specifies a penalty for delay in completion of work beyond the due date as follows: ₹250 for the 1st day, ₹310 for the 2nd day, ₹370 for the 3rd day, and so on. If the contractor pays a total fine of ₹6,960, find the number of days by which the work was delayed.
- 113
- 212✓
- 311
- 410
Correct answer
12