Mathematics · Contract Costing
A construction firm entered a ₹20,00,000 contract in January 2024, expected to complete in 3 years. Due to a 30% increase in material prices and 10% rise in labour rates, the escalation clause allows for compensation of 60% of the increased cost. By March 2025, the total material and labour cost increased by ₹3,00,000 due to price rise. What additional amount should be credited to the Contract Account under the escalation clause?
- 1₹1,80,000✓
- 2₹2,40,000
- 3₹3,00,000
- 4₹1,20,000
Correct answer
₹1,80,000
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Contract Costing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Contract Costing