Computer · Estimation and Costing
A construction company is preparing to bid for a large infrastructure project. The initial design phase is complete, but detailed engineering drawings are not yet available. Based on available information like area, volume, and preliminary specifications, the company prepares an estimate. Which type of cost estimate is the company likely to use?
- 1Quantity Survey Estimate
- 2Detailed Estimate
- 3Bid Estimate
- 4Preliminary Estimate✓
Correct answer
Preliminary Estimate
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Estimation and Costing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Estimation and Costing