A construction company hired 1,000 persons to construct a building in 77 days. After 44 days, the company realized that only 40% of the work had been finished. How many additional persons must the company hire to complete the work on the scheduled time?
- 13,000
- 21,000✓
- 34,000
- 42,000
Correct answer
1,000