Accounting · Management Accounting
A company uses absorption costing with a predetermined hourly overhead absorption rate. The following situations arose last month: 1. Actual hours worked exceeded planned hours 2. Actual overhead expenditure exceeded planned expenditure What individual effect would each of these situations have on the absorption of overheads?
- 1Both would cause overheads to be under absorbed
- 2Both would cause overheads to be over absorbed
- 31 would cause under absorption and 2 would cause over absorption
- 41 would cause over absorption and 2 would cause under absorption✓
Correct answer
1 would cause over absorption and 2 would cause under absorption
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Accounting?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Management Accounting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Accounting · Management Accounting