A company is planning to manufacture a new battery using an existing machine. Producing every 1,000 units takes 14 hours. The historical data for machine hours and total maintenance costs over the last four years are as follows: - Year 1: 5,000 hours, $850,000 - Year 2: 4,400 hours, $735,000 - Year 3: 4,850 hours, $815,000 - Year 4: 1,800 hours, $450,000 If the maximum capacity of the machine is 5,000 hours, what is the estimated maintenance cost (using the high-low method) if production is at 80% of maximum capacity?
- 1$735,000
- 2$500,000
- 3$593,000✓
- 4$575,000
Correct answer
$593,000
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Cost and Management Accounting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Cost and Management Accounting