A company commenced work on the construction of a significant asset for one of its customers on 1 May 20X5. Construction is scheduled to run for two years and the total contract price is $5m. At 31 December20X5, the following details are obtained in relation to the contr act: - The percentage complete was 50%. - Amounts invoiced to the customer totalled $1.7m. - Amounts received from the customer totalled $0.8m. What is the total amount that should be included in the statement of financial position as at 31 December 20X5 as a contract asset?
- 1$2.5m
- 2$1.7m
- 3$0.8m✓
- 4$0.9m
Correct answer
$0.8m
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Financial Accounting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Financial Accounting