General Studies · Industrial Engineering and Operations Research
A clutch manufacturing factory operates for eight hours a day, five days a week. One 30-minute meeting and an hour of maintenance are scheduled for each week. Employees receive two daily 15-minute breaks in addition to a 30-minute lunch break. What will be the takt time if the rate of customer demand for the clutches is 50 orders per day?
- 18.04 minutes
- 27.28 minutes
- 36.84 minutes✓
- 46.48 minutes
Correct answer
6.84 minutes
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Engineering and Operations Research?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Industrial Engineering and Operations Research