A certain number of persons can complete a piece of work in 35 days working 9 hours a day. If the number of persons is decreased by 50%, then how many hours a day should the remaining persons work to complete the work in 60 days?
- 114
- 2912
- 31012✓
- 412
Correct answer
1012