A can lay railway track between two given stations in 19 days and B can do the same job in 16 days. With the help of C, they did the job in 5 days only. Then, C alone can do the job in how many days?
- 19101129 days
- 220101129 days
- 313101129 days
- 411101129 days✓
Correct answer
11101129 days