A can lay a railway track between two given stations in 8 days and B can do the same job in 24 days. With the help of C, they finish the job together in just 3 days. How many days will C alone take to complete the job?
- 16 days✓
- 29 days
- 37 days
- 48 days
Correct answer
6 days