Mathematics · Time and Work
A can lay a railway track between two given stations in 18 days, and B can do the same job in 16 days. With the help of C, they finished the job in just 3 days. How many days would C alone take to do the job?
- 1431 days✓
- 2231 days
- 31031 days
- 41431 days
Correct answer
431 days
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Time and Work?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Time and Work