Mathematics · Time and Work
A can finish a work in 25 days, and B can do the same work in 15 days. B worked for 10 days and left the job. A alone can finish the remaining work in how many days?
- 1713 days
- 2613 days
- 3813 days✓
- 4513 days
Correct answer
813 days