Mathematics · Time and Work
A can finish a piece of work in 9 days, while B can finish the same work in 18 days. They begin the work together, but after 2 days B leaves and A completes the remaining work alone. If the total wages for completing the entire work is Rs. 13,500, find A's share (in Rs.).
- 111,500
- 210,000
- 39,000
- 412,000✓
Correct answer
12,000
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Time and Work?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Time and Work