A can do a work in 8 days and B can do it in 6 days. They have undertaken to do that work together for Rs. 1,800. If they complete that work in 3 days with the help of C, then C's share of the amount (in Rs.) is:
- 1225✓
- 2250
- 3275
- 4325
Correct answer
225