Mathematics · Time and Work
A can do a work in 12 days and B in 16 days. A works alone for 3 days, then B joins him and they complete the remaining work together. How many total days did it take to complete the work?
- 17.5 days
- 28.14 days✓
- 310 days
- 49 days
Correct answer
8.14 days