Mathematics · Time and Work
A can do a piece of work in 60 days, and B can do it in 50 days. Both work together for 10 days, after which A leaves. How long will B take to complete the remaining work?
- 130 days
- 23523 days
- 33123 days✓
- 43023 days
Correct answer
3123 days