Mathematics · Time and Work
A can do a piece of work in 4 days and B can do the same work in 8 days. They worked together for 2 days and then B left. After that, A alone completed the remaining work. In how many total days was the work completed?
- 13✓
- 292
- 352
- 44
Correct answer
3
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Time and Work?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Time and Work