A can do a certain work in 60 days. B is 25% more efficient than A, while C is 20% more efficient than B. B alone worked and completed 37.5% of the total work, and then left. A and C together completed the remaining work. In how many days was the entire work completed?
- 135 days
- 233 days✓
- 332 days
- 430 days
Correct answer
33 days