Mathematics · Time and Work
A can complete in 2 days as much of a task as B can complete in 3 days, and B can complete in 4 days as much of the task as C can complete in 5 days. In how many days will A, B, and C together complete the task if A alone can complete it in 22 days?
- 114 days
- 211 days
- 310 days✓
- 412 days
Correct answer
10 days