Mathematics · Time and Work
A can complete a work in 'k' days. B can complete the same work in 'l' days. How many days will it take to complete the work if they work together?
- 1k + lkl
- 2klk + l✓
- 31 + kl
- 41k + l
Correct answer
klk + l
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Time and Work?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Time and Work