Mathematics · Time and Work
A can complete a work in 8 days, B can complete the same work in 12 days, and C can complete it in 6 days. B and C worked together for x days, and the remaining work was completed by A alone in (x + 2) days. Find what percentage of the total work will be completed if A alone works for (x + 4) days.
- 195%
- 290%
- 375%✓
- 4100%
Correct answer
75%