A can complete a work in 20 days, while B can complete the same work in 25 days. Both worked together for 10 days and then C alone completed the remaining work in 10 days. In how many days will A, B, and C together complete the same work?
- 112 days
- 28 days
- 35 days✓
- 410 days
Correct answer
5 days