Mathematics · Time and Work
A can complete a work in 16 days and B can complete the same work in 20 days. If both work together for 4 days and then A leaves, how many more days will it take B to complete the remaining work?
- 112 days
- 29 days
- 311 days✓
- 410 days
Correct answer
11 days
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Time and Work?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Time and Work