Mathematics · Work and Time
A can complete a work in 16 days and B can complete it in 24 days. They work together for 5 days, then A leaves. How many more days will B take to complete the remaining work?
- 113.5 days
- 211.5 days✓
- 312.5 days
- 410.5 days
Correct answer
11.5 days
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Work and Time?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Work and Time