Mathematics · Time and Work
A can complete a task in the same time in which B and C work together. If A and B could complete it jointly in 10 days and C alone in 50 days, then B could complete it independently in:
- 123 days
- 225 days✓
- 327 days
- 426 days
Correct answer
25 days