Mathematics · Time and Work
A can complete a task in 30 days, and B can complete the same task in 40 days. They work together for 10 days, and then C joins them and completes the remaining work in 5 days. How long will C alone take to complete the entire task?
- 125 days
- 226 days
- 340 days✓
- 427 days
Correct answer
40 days