A can complete a task in 12 days and B can complete the same task in 18 days. They start working together but A leaves after working for only 2 days. The remaining work is completed by B alone. If the total wage for the complete task is ₹2,400, then what is B's share (in ₹)?
- 11600
- 21800
- 31200
- 42000✓
Correct answer
2000