Mathematics · Time and Work
A can complete a task in 10 days, while B can finish the same task in 12 days. They decide to work alternately, with A starting the work on the first day. How many days will it take for them to complete the entire task?
- 110.5 days
- 210.2 days
- 310.83 days✓
- 410.4 days
Correct answer
10.83 days
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Time and Work?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Time and Work